Chanyanya Pilot Irrigation Project, Zambia [991]

PIDG Company: InfraCo Africa Development
PIDG Commitment (US$m): 1.60
Co-Financed with other PIDG entity: No
Project Country: Zambia
Region: Sub-Saharan Africa
DAC Type: Least Developed Country
Fragile State Type: Other
Sector: Agriculture-supporting infrastructure
Climate Change Mitigation Tier: 3
Climate Change Adaptation: 3
Status: Financially Closed
Date of Commitment / Signing: 01/2006
Date of Financial Close: 01/2009
Post-Completion Monitoring completed: Yes
PCM Year: 2009
Date of Operation expected: 11/2008
Date of Operation actual: 11/2008
Total Investment Commitment - Predicted (US$m): 5.77
Development Finance Investment Commitment - Predicted (US$m): 2.99
Total Investment Commitment (Actual) (US$m): 5.74
Development Finance Institution Investment (Actual) (US$m): 2.96
People with Access to New Infrastructure - Predicted: 1134
People with Access to New Infrastructure - Male (Predicted): 708
People with Access to New Infrastructure - Female (Predicted): 426
People with Access to New Infrastructure (Actual): 1033
People with Access to New Infrastructure - Male (Actual): 645
People with Access to New Infrastructure - Female (Actual): 388
Fiscal Impact - Up Front Fees To Government (Actual) (US$m): 0.12
Short Term Jobs Created - Predicted: 95
Short Term Jobs Created (Actual): 95
Long Term Jobs Created - Predicted: 130
Long Jobs Created (Actual): 26