Bugoye Hydro Power Plant, Uganda [819]
PIDG Company: | EAIF |
PIDG Commitment (US$m): | 33.85 |
Co-Financed with other PIDG entity: | No |
Project Country: | Uganda |
Region: | Sub-Saharan Africa |
DAC Type: | Least Developed Country |
Fragile State Type: | Fragile State |
Sector: | Power/Energy |
Climate Change Mitigation Tier: | 1 |
Climate Change Adaptation: | 3 |
Status: | Financially Closed |
Date of Commitment / Signing: | 01/2008 |
Date of Financial Close: | 01/2008 |
Post-Completion Monitoring completed: | Yes |
PCM Year: | 2011 |
Date of Operation actual: | 10/2009 |
Total Investment Commitment - Predicted (US$m): | 62.65 |
Total Private Sector Investment Commitment - Predicted (US$m): | 6.75 |
Development Finance Investment Commitment - Predicted (US$m): | 55.90 |
Total Investment Commitment (Actual) (US$m): | 60.52 |
Total Private Sector Investment (Actual) (US$m): | 5.72 |
Development Finance Institution Investment (Actual) (US$m): | 54.80 |
People with Access to Improved Infrastructure - Predicted: | 381395 |
People with Access to Improved Infrastructure - Male (Predicted): | 236560 |
People with Access to Improved Infrastructure - Female (Predicted): | 144835 |
People with Access to Improved Infrastructure (Actual): | 353488 |
People with Access to Improved Infrastructure - Male (Actual): | 219251 |
People with Access to Improved Infrastructure - Female (Actual): | 134237 |
Fiscal Impact - Up Front Fees To Government (Predicted) (US$m): | 0.20 |
Fiscal Impact - Total Taxes Paid (Predicted) (US$m): | 10.00 |
Short Term Jobs Created - Predicted: | 500 |
Short Term Jobs Created (Actual): | 927 |
Long Term Jobs Created - Predicted: | 10 |
Long Jobs Created (Actual): | 22 |