Results Monitoring Database
Tororo Solar PV, Uganda [1364]
PIDG Company: | EAIF |
PIDG Commitment (US$m): | 7.33 |
Co-Financed with other PIDG entity: | No |
Project Country: | Uganda |
Region: | Sub-Saharan Africa |
DAC Type: | Least Developed Country |
Fragile State Type: | Fragile State |
Sector: | Power/Energy |
Climate Change Mitigation Tier: | 1 |
Climate Change Adaptation: | 3 |
Status: | Financially Closed |
Date of Commitment / Signing: | 11/2016 |
Date of Financial Close: | 11/2016 |
Post-Completion Monitoring completed: | Yes |
PCM Year: | 2018 |
Date of Operation expected: | 11/2017 |
Date of Operation actual: | 11/2017 |
Total Investment Commitment - Predicted (US$m): | 19.66 |
Total Private Sector Investment Commitment - Predicted (US$m): | 4.99 |
Development Finance Investment Commitment - Predicted (US$m): | 14.67 |
Total Investment Commitment (Actual) (US$m): | 17.50 |
Total Private Sector Investment (Actual) (US$m): | 2.90 |
Development Finance Institution Investment (Actual) (US$m): | 14.60 |
People with Access to Improved Infrastructure - Predicted: | 67037 |
People with Access to Improved Infrastructure - Male (Predicted): | 41556 |
People with Access to Improved Infrastructure - Female (Predicted): | 25481 |
People with Access to Improved Infrastructure (Actual): | 67037 |
People with Access to Improved Infrastructure - Male (Actual): | 41556 |
People with Access to Improved Infrastructure - Female (Actual): | 25481 |
Short Term Jobs Created - Predicted: | 240 |
Short Term Jobs Created (Actual): | 270 |
Long Term Jobs Created - Predicted: | 13 |
Long Jobs Created (Actual): | 4 |