Results Monitoring Database

K-Electric [1546]

PIDG Company: GuarantCo
PIDG Commitment (US$m): 47.50
Co-Financed with other PIDG entity: No
Project Country: Pakistan
Region: South Asia
DAC Type: Lower Middle Income Country or Territory
Fragile State Type: Fragile State
Sector: Power/Energy
Climate Change Mitigation Tier: 3
Climate Change Adaptation: 3
Status: Financially Closed
Date of Commitment / Signing: 09/2019
Date of Financial Close: 09/2019
Post-Completion Monitoring completed: Yes
PCM Year: 2020
Date of Operation expected: 06/2020
Date of Operation actual: 01/2020
Total Investment Commitment - Predicted (US$m): 50.00
Total Private Sector Investment Commitment - Predicted (US$m): 50.00
Total Investment Commitment (Actual) (US$m): 50.00
Total Private Sector Investment (Actual) (US$m): 50.00
People with Access to Improved Infrastructure - Predicted: 76000
People with Access to Improved Infrastructure - Male (Predicted): 47937
People with Access to Improved Infrastructure - Female (Predicted): 28063
People with Access to Improved Infrastructure (Actual): 76000
People with Access to Improved Infrastructure - Male (Actual): 47937
People with Access to Improved Infrastructure - Female (Actual): 28063
Short Term Jobs Created (Actual): 264