Senergy 2, Solar Park, Senegal [1389]

PIDG Company: GAP
PIDG Commitment (US$m): 21.10
Co-Financed with other PIDG entity: No
Project Country: Senegal
Region: Sub-Saharan Africa
DAC Type: Least Developed Country
Fragile State Type: Other
Sector: Power/Energy
Climate Change Mitigation Tier: 1
Climate Change Adaptation: 3
Status: Financially Closed
Date of Commitment / Signing: 09/2016
Date of Financial Close: 09/2016
Post-Completion Monitoring completed: Yes
PCM Year: 2016
Date of Operation expected: 09/2016
Date of Operation actual: 12/2016
Total Investment Commitment - Predicted (US$m): 30.50
Total Private Sector Investment Commitment - Predicted (US$m): 9.50
Development Finance Investment Commitment - Predicted (US$m): 21.00
Total Investment Commitment (Actual) (US$m): 30.50
Total Private Sector Investment (Actual) (US$m): 9.50
Development Finance Institution Investment (Actual) (US$m): 21.00
People with Access to Improved Infrastructure - Predicted: 160000
People with Access to Improved Infrastructure - Male (Predicted): 98133
People with Access to Improved Infrastructure - Female (Predicted): 61867
People with Access to Improved Infrastructure (Actual): 160000
People with Access to Improved Infrastructure - Male (Actual): 98133
People with Access to Improved Infrastructure - Female (Actual): 61867
Fiscal Impact - Total Taxes Paid (Predicted) (US$m): 1.10
Fiscal Impact - Total Taxes Paid (Actual) (US$m): 1.10
Short Term Jobs Created - Predicted: 80
Short Term Jobs Created (Actual): 80
Long Term Jobs Created - Predicted: 24
Long Jobs Created (Actual): 24