Results Monitoring Database

Nyumba Ya Akiba Cement project, Democratic Republic of Congo [1255]

PIDG Company: EAIF
PIDG Commitment (US$m): 30.00
Co-Financed with other PIDG entity: No
Project Country: Congo (D.R.)
Region: Sub-Saharan Africa
DAC Type: Least Developed Country
Fragile State Type: Fragile State
Sector: Manufacturing
Climate Change Mitigation Tier: 3
Climate Change Adaptation: 3
Status: Loan prepaid / G'tee pre-redeemed
Date of Commitment / Signing: 11/2014
Date of Financial Close: 11/2014
Post-Completion Monitoring completed: Yes
PCM Year: 2016
Date of Operation expected: 05/2017
Date of Operation actual: 12/2016
Total Investment Commitment - Predicted (US$m): 270.00
Total Private Sector Investment Commitment - Predicted (US$m): 180.00
Development Finance Investment Commitment - Predicted (US$m): 90.00
Total Investment Commitment (Actual) (US$m): 270.00
Total Private Sector Investment (Actual) (US$m): 180.00
Development Finance Institution Investment (Actual) (US$m): 90.00
Fiscal Impact - Total Taxes Paid (Predicted) (US$m): 29.20
Fiscal Impact - Total Taxes Paid (Actual) (US$m): 29.20
Short Term Jobs Created - Predicted: 360
Short Term Jobs Created (Actual): 360
Long Term Jobs Created - Predicted: 270
Long Jobs Created (Actual): 115